Date Posted : October 9, 2021


The project's scope included supply, installation and commissioning of a sanitary pump station, installations of 460 meters of 200mm PVC watermain, 200 meters of 300mm PVC watermain, 500 meters of 200mm sanitary sewer, 300 meters of 450mm storm sewer, 2,400 meters of hydro ducts, 2,000 meters of Shaw and Telus ducts, 16 street lights, concrete curbing and pathways construction.



The delivery of 6 residential roads servicing over 60 lots has been completed for the Executive Group who have already began pre-sales and building construction on the site in Tsawwassen.

Complete Utility Contractors would like to thank everyone involved in this project to develop brand new master planned community in Greater Vancouver's gorgeous Tsawwassen district, including the Tsawwassen First Nations and the project team at Executive Group for the opportunity.