The construction of district energy systems including insulated steel pipe, leak detection systems, communication conduit and other related works along Whalley Blvd, King George Blvd and Central Ave in the City of Surrey.



  • Completion Date: January 2022
  • Start Date: March 2021
  • Client: City of Surrey

Complete Utility Contractors Ltd. recently started the supply and install of 2km of Direct Energy Distribution Piping System (DPS) expansion for the City of Surrey. A portion of the project requires installation down the center of King George Blvd in Surrey while maintaining traffic flows on each side of the pipe installation. The project also includes all required utility relocates to facilitate installation.

This project is comprised of 1100 meters of 100mm to 400mm diameter pipe.